System Extensions
Types of
Project Actions:
New
commercial construction,
new residential
development, and
renovation of an existing
facility to use for a new
purpose
-
-
-
-
-
-
If CWD has required the developer
to install a water main or other changes to the water
system to obtain water service, the developer must enter
into a SEA with CWD and satisfy all the conditions.
-
Contact CWD Project Administrator
to prepare the SEA package. Required information
includes preliminary plans and proposed number &
sizes of water meters.
-
The SEA package is sent to the
developer for review and signature.
-
The developer submits the signed
and notarized SEA package with appropriate deposit.
-
CWD Board of Water Commissioners
(Board) issues a resolution approving the SEA.
Contact:
Contract Administrators at
253-631-0565
ext.145 or
systemextensions@covingtonwater.com.
Back to Top
-
Hire a licensed Civil Engineer to
design the water main and other facilities to be
installed.
-
Plan review process will start
after the SEA is approved by CWD Board.
-
Schedule a pre-design meeting
with CWD staff engineers prior to the start of water
main design.
-
Plans must conform to CWD
Standards and Specifications and other requirements
by local jurisdictions.
-
Return period and number of
review cycles depend on the quality of the submitted
plans. Engineering notes and requirements are listed
in the Engineer/Contractor Information Sheets.
-
Fire Marshal’s approval of the
plans is required prior to final approval by CWD.
Contact: CWD Staff Engineers at
253-631-0565 or
engineering@covingtonwater.com.
Back to Top
-
Hire a licensed contractor for
construction of the water system improvement and
inform CWD of the contractor’s name, address, and
phone number.
-
Provide easements to CWD for any
improvements located outside project boundary and
public ROW.
-
The contractor or engineer
provides CWD traffic control plans for ROW permit
application (if needed). CWD will make an
application to the appropriate jurisdiction.
-
Material Submittals are required
for CWD review and approval.
-
A Preconstruction Meeting
requires 5 working days advance notice. The meeting
can be requested only when all applicable
requirements have been received.
-
All applicable ROW permits
received
-
CWD Approval of Material
Submittals
-
CWD Approval of water
extension plans
-
The developer and contractor must
attend the preconstruction meeting to discuss the
construction schedule, standards, requirements, and
start date.
-
A Meter Installation,
Application, & Agreement Form will be provided to
the developer for commercial projects at the
Preconstruction Meeting.
-
No deviation from the approved
plans will be allowed. A request for any plan
changes must be made by the engineer and approved by
CWD.
-
CWD Inspector will regularly be
present at the site to inspect the construction for
conformance with plans and Standards.
-
CWD will perform required tests
and final inspection.
-
See notes and requirements for
ROW permit application, material submittals, and
construction in the Engineer/Contractor Information
Sheets.
Contact:
Contract Administrators at
253-631-0565
ext.145 or
systemextensions@covingtonwater.com.
Back to Top
Contact:
Contract Administrators at
253-631-0565
ext.145 or
systemextensions@covingtonwater.com.
Back to Top
-
After the SEA has been accepted,
each lot must have a separate Water Availability
Certificate (WAC) for a building
permit.
-
A WAC application form
can either be mailed, picked up at CWD,
or downloaded
here (MS Word
document) Applications can be
requested in increments of 10 to 15 at a time.
-
Processing and application fee
must be paid at time of submittal.
-
For accepted projects, CWD has
as-builts on file and site plans will not be
required.
Contact:
Contract Administrators at
253-631-0565
ext.120 or
wateravailability@covingtonwater.com.
Back
to Top
Residential Plats
-
Homeowner comes to CWD front
desk, requests and completes the Meter Installation,
Application, & Agreement Form, as the control
numbered forms cannot leave CWD office.
-
CWD verifies if the property was
included in the CWD Board accepted project.
-
Submit the form and pay drop-in
installation fee for dual meters.
-
CWD will install the meters in
approximately 2-3 weeks from date of submittal.
Commercial Projects
-
The developer completes the Meter
Installation, Application, & Agreement Form at the
Preconstruction Meeting and pays for applicable
meters. Notify CWD Project Administrator in advance
of the meeting with size and numbers of the proposed
water meters.
-
The contractor installs any
required backflow prevention devices, has them
tested by a state certified tester, and gets
approval from CWD’s backflow prevention specialist.
-
CWD delivers the meters and the
contractor installs them. The meters will be locked
until the project is accepted by CWD Board.